Thunderhorse

Heerema – HMC

HMC scope: HMC BV were contracted by BP Exploration for the deep see scope for the Thunderhorse project.

The Thunder Horse subsea contract scope involved:

22 km of production and test flowlines (8 flowlines), 20 km of production and test Steel Catenary Risers (5 SCR’s), 2 large manifolds of 300 short tons each, with suction pile foundation, 2 smaller manifolds of 150 short tons each, with suction pile foundation, 13 PLET walking anchors, 18ft diameter hold back anchors (suction piles), 21 Pipeline End 

FT Scope: Dynamic riser (SCR) fabrication.

Location: HQ HMC Leiden, the Netherlands and offshore Gulf of Mexico